Observatory Update, 2 – 3 May 2015: Railings Going Up!

IMG_1734

On 2 May Adrian and Charles received a delivery of yellow cedar and began putting up the deck railings for the observatory. Meanwhile Mike worked on the mount and pier, and David showed up to work on wiring the solar panels into the charging system.

Battery charging system installed

Battery charging system installed

Railing work 3 May

Railing work 3 May

The next day Adrian and Charles returned in overlapping shifts to put up more railing while Mike worked on the telescope mount alignment.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: